Eight converted bitcoin miners hold about 5.7 GW of AI leases. Under 1 GW is live. The rest is contracted and awaits phased construction and energization.

Eight former bitcoin miners now lease data center capacity to AI tenants: Core Scientific, Applied Digital, Galaxy, TeraWulf, Cipher Digital, Riot Platforms, Hut 8 and CleanSpark. As of August 21, 2026, their filings put roughly 5.7 gigawatts under contract, measured in critical IT load with one caveat explained below, and about 870 megawatts delivered and billing. The remainder has a construction schedule attached.
None of it came from the mining computers. Bitcoin is mined on SHA-256 ASICs, chips built to run one hash function and nothing else; they have no AI application, and when a site converts, they are written down or sold. What carried over was the power estate: land, substations, transformers, interconnection rights, utility relationships, and years of experience operating very large loads that can be switched off on command. Applied Digital describes "the interconnection rights necessary to energize high-density compute at scale" (FY2026 10-K); CleanSpark's chief financial officer calls its sites "a portfolio of scarce, grid-connected power assets" (8-K, July 14, 2026). The contracted figures are real, the live figures are real, and the distance between them is the time it takes to build a data hall on a site whose electrical connection already exists.
Gross power is not critical IT load. Gross is the utility capacity at the fence; critical IT is what the racks can draw once cooling, distribution losses, and redundancy have taken their share, and it governs how an operator manages a supercomputer's power envelope. Cipher's Black Pearl lease is 300 MW gross, and 216 MW critical IT; Galaxy's Helios Phase I is 200 MW gross and 133 MW critical IT. Those two disclosed ratios run 0.66 to 0.72.
Operational is not contracted, and contracted is not pipeline. A lease is a legal state, an energized hall is a physical one, and a load request filed with a grid operator is neither.
Base term is not extension-inclusive value. Riot's frontier-lab lease is $9.1 billion over its initial 20 years and $16.1 billion if both five-year options are exercised. The landlord has granted those options, and the tenant has not committed to exercising them, so both figures accurately describe different things.
Then the cohort's own units. Core Scientific reports "leased customer power capacity," which it defines as committed non-redundant customer IT load; Hut 8 reports IT megawatts alongside "utility capacity"; Cipher quotes gross at the portfolio level and critical IT per lease; the other five report critical IT. Every one of these companies disclosed correctly in its own terms, but the terms do not match, and an aggregate that adds them without saying so measures four quantities with one number.
Unit is critical IT unless the cell says otherwise; "live" uses each company's own verb, and revenue is the company-stated contracted amount over the initial term.
Company | AI tenant(s) | Contracted (critical IT MW) | Gross MW, where disclosed | Live / billing | First rent or energization | Base-term revenue | With extensions | As of / source |
|---|---|---|---|---|---|---|---|---|
Core Scientific | CoreWeave (5 sites); AMD (Pecos TX, Muskogee OK, Hunt County TX); unnamed neocloud with AMD credit support (Auburn AL, Dalton GA) | 1,119 MW "leased customer power" (590 CoreWeave + 377 AMD + 152 neocloud; the AMD and neocloud leases are stated as critical IT) | 2,115 MW gross utility capacity under control | 437 MW billing (mid-July 2026) | CoreWeave billing began 2025 | ">$24B potential contracted revenue"; AMD anchor ">$14B" | Not disclosed (15 yr + three 5-yr options on AMD/neocloud) | |
Applied Digital | CoreWeave (Polaris Forge 1, 400); hyperscaler A (PF2, 200); hyperscaler B (Delta Forge 1, PF3, Delta Forge 2; 810) | 1,410 MW | Not disclosed per lease | 175 MW (June 30, 2026) | Oct 2025 | ~$36.2B over 15-yr base terms | ~$86B if all renewals exercised | |
Galaxy | CoreWeave (Helios, Phases I-III) | 526 MW | 800 MW | 133 MW (200 MW gross), in service by June 30, 2026 | Q2 2026 | Not disclosed as a total; "$1.2B+" anticipated average annual revenue | Not disclosed (15 yr + two 5-yr options) | |
TeraWulf | Core42 (60) and Fluidstack with Google backstop (378) at Lake Mariner; Anthropic (401) at Justified | 839 MW (438 + 401) | Justified up to ~480 MW; Lake Mariner ~500 MW near term | 102 MW (July 2026) | Core42 leases commenced Jul/Aug 2025 | Anthropic ~$19B (20 yr); Lake Mariner totals not restated | Anthropic ~$33B with both 5-yr extensions | |
Cipher Digital | Fluidstack with Google backstop (Barber Lake, 168); Amazon Data Services (Black Pearl, 216); AWS (Stingray, 70) | 454 MW | 644 MW lease-supported (244 + 300 + 100); company quotes "700 MW contracted gross" on a site basis | First Black Pearl tranche delivered Aug 2026, rent commenced; MW not disclosed | Aug 2026 | ~$11.4B across three leases; Stingray ~$2.0B, rent targeted Apr 2027 | Barber Lake ~$7B with extensions; others not disclosed | |
Riot Platforms | AMD (50, Rockdale); unnamed frontier AI lab (191, Rockdale) | 241 MW | Not disclosed per lease; Rockdale ~700 MW developed | 25 MW (AMD, May 2026) | Jan 2026 | ~$9.8B combined; frontier lab $9.1B over 20 yr | Frontier lab ~$16.1B with both options | |
Hut 8 | Fluidstack (River Bend, 245); one investment-grade tenant (Beacon Point Ph1 352 + Ph2 352) | 949 MW | 1,330 MW utility (330 + 1,000) | 0 MW (Q2 colocation revenue of $1.3M is legacy hosting) | Beacon Point energization Q1 2027; River Bend first hall Q2 2027; Beacon Point first hall Q3 2027 | ~$26.6B aggregate; Beacon Point ~$19.6B | Beacon Point ~$50.2B if all renewals exercised | |
CleanSpark | Unnamed investment-grade global technology company (Sandersville GA) | 175 MW | Not disclosed | 0 MW | Deliveries from Q4 2027 | ~$6.6B over 20-yr triple-net | ~$11.6B with two 5-yr extensions |
Seven of the eight report contracted capacity in critical IT, and together they hold 4,594 MW. Core Scientific's 1,119 MW of leased customer power is comparable in kind but not in label; adding it gives about 5.7 GW, with that caveat stated. Disclosed live capacity is 872 MW, plus a first Black Pearl tranche whose size Cipher has not published: roughly one megawatt billing for every 6.5 under contract. Disclosed base-term revenue across the eight comes to about $134 billion. Bernstein analysts, as reported by The Block on July 15, 2026, count 7 GW across 19 miner-related deals worth more than $135 billion; their set is wider than these eight, so it corroborates.
Every megawatt figure a company publishes sits on one rung of the same ladder. The rungs below are the convention this publication will use for the sector; the examples come from the cohort's Q2 2026 filings, with the filing's own verb.
Rung | State | Cohort examples (filing verb) |
|---|---|---|
1. Operational / billing | Tenant is paying for delivered critical IT | Core Scientific 437 MW ("billing for 437 MW"); Applied Digital 175 MW ("total live capacity"); Galaxy 133 MW ("in service"); TeraWulf 102 MW ("revenue-generating"); Riot 25 MW ("commissioned capacity online"); Cipher, first Black Pearl tranche ("rent has commenced") |
2. Contracted, under construction | Executed lease; halls in civil, structural or MEP work | Applied Digital ~1,235 MW ("approximately 1.4 GW already under construction"); Hut 8 949 MW IT / 1,330 utility ("executed definitive commercial agreements and commenced construction"); Cipher 454 MW (Barber Lake "partial occupancy," Black Pearl "MEP fit-out," Stingray "underground electrical work has commenced"); TeraWulf 336 MW (CB-4/CB-5); Galaxy 260 MW (Phase II "foundation work now underway"); Core Scientific 195 MW; Riot 25 MW |
3. Contracted, construction not materially underway | Executed lease; delivery dated but site work not disclosed as begun | Core Scientific 377 MW AMD + 152 MW neocloud (signed July 27, 2026); TeraWulf 401 MW Anthropic ("initial delivery expected in the second half of 2027"); Riot 191 MW ("initial 96 IT MW expected in December 2027"); CleanSpark 175 MW ("expected to begin in Q4 2027"); Galaxy 133 MW Phase III ("starting in 2027") |
4. Power approved or energized, no AI tenant | Interconnection granted or live; load is mining or unleased | Galaxy 830 MW gross ("approved capacity at Helios not yet under lease"); Core Scientific 685 MW unleased; Cipher 207 MW Odessa ("currently energized") + 270 MW Reveille/Ulysses ("interconnection approved"); Riot ~459 MW Rockdale + 400 MW Corsicana (mining); TeraWulf up to 1 GW Muskie ("contracted electric service," from Q4 2028); Hut 8 710 MW under management; CleanSpark ~300 MW Sealy + 300 MW Brazoria |
5. Interconnection under study | Load request filed; outcome depends on the grid operator | Galaxy 2,000 MW Helios III-IV ("progressing through ERCOT's interconnection process") + ~1,600 MW Caspian/Selene; Cipher ~2,900 MW Colchis/Mikeska/McLennan/Apollo ("expected to be included in Batch Zero") + 700 MW adjacent, 2030+; Riot ~600 MW Corsicana; Hut 8 1,000 MW River Bend expansion; TeraWulf 250 MW Lake Mariner |
6. Site controlled or optioned, no interconnection filing disclosed | Land and a power study | Hut 8 1,880 MW "under exclusivity"; TeraWulf ~400 MW Lake Hawkeye + up to 1 GW Chesapeake; Cipher 500 MW Milsing; part of Applied Digital's "over 3 GW" active pipeline |
7. Marketing / theoretical | Named in a deck or partnership envelope; little or no capital committed | Hut 8 5,400 MW "under diligence"; Core Scientific "up to 2.5 GW" AMD envelope, 1,925 MW reservation right; Applied Digital "more than 5 GW" extended pipeline, 1.7 GW "actively marketing"; CleanSpark 885 MW Texas portfolio under LOI |
Two company totals show why a single pipeline number misleads. Cipher describes "5.3 GW across 11 sites at various stages of interconnection." Decomposed, that is a first tranche on rung one, 454 MW of contracted critical IT on rung two, 477 MW of energized or approved mining-era interconnection on rung four, about 3.6 GW in or behind ERCOT's Batch Zero study on rung five, and 500 MW of optioned land on rung six. Hut 8's 8,660 MW "development pipeline" (Q2 2026 release) spreads the same way: 1,330 MW of utility capacity under construction, 50 MW under development, 1,880 MW under exclusivity, and 5,400 MW under diligence.
Neither company hides this; both publish the decomposition. The top-line number is what travels, though, and the rungs stay home. Cipher's August investor presentation states "907 MW of operating and contracted capacity today," footnoted as gross megawatts for executed HPC leases plus currently operating bitcoin self-mining (8-K, August 4, 2026, EX-99.2). The label, not the number, drops off in secondary citation.
Concurring in FERC's June 18 show-cause orders on large-load interconnection (Docket EL26-68-000), Commissioner David Rosner wrote that speculative requests "clog up load interconnection queues, divert resources, and distort forecasts," and modeling projects that never materialize leads "to double counting." It is the same tangle of speculative requests and committed projects this publication described in the 100-gigawatt pipeline in March, and a rung-five figure read as rung one is the same error.
Galaxy's Helios campus in Dickens County, Texas, is the clearest single record of what transfers in a conversion and what does not.
Argo Blockchain's FY2022 annual report described its March 2021 purchase as "a strategically-located piece of land with a secured interconnection agreement with the Texas grid for up to 800 MW of electricity" (Form 20-F). Argo paid roughly $5 million in stock and sold the site to Galaxy in December 2022 for $65 million. Galaxy's FY2025 10-K describes "the full 800 MW of high-voltage capacity for which we are already fully approved from ERCOT" (10-K). CoreWeave's three Helios leases total 800 MW gross. The interconnection Argo secured in 2021 is the interconnection CoreWeave is leasing in 2026.
In Galaxy's Q2 2026 10-Q, mining equipment is carried at $79.25 million as of both December 31, 2025 and June 30, 2026, with accumulated impairment of $88.2 million that is identical at both dates; the write-down happened in 2025. The FY2025 MD&A records an "$87.3 million impairment of mining equipment and related infrastructure and $12.3 million of disposals of mining equipment net carrying value associated with the data center conversion." Data center infrastructure rose from $67.7 million to $1.70 billion between the two balance-sheet dates, but that is not $1.6 billion of fresh spend in six months: construction in progress fell from $1.34 billion to $512 million over the same period, and the footnote says infrastructure assets were moved into WIP during 2025 "as they are undergoing enhancements." Much of the jump is reclassification back out.
So the mining compute was impaired, partly disposed of, and displaced; the halls were rebuilt; the substation, the transformers, and the ERCOT approval were kept. Cipher's February notes deck says the same of Black Pearl: "~85% of the infrastructure currently deployed at Black Pearl is expected to be utilized for the AWS project" (8-K EX-99.1). The electrical yard transfers; the hall is gutted and the mining hardware leaves the books.
CoreWeave came out of crypto mining and now runs AI compute. By its own account, the company mined its first block on the Ethereum network in 2016, and "one GPU turned into hundreds, then tens of thousands via strategic acquisitions of distressed hardware during the 'crypto-winter' of 2018/2019." It bought a rendering platform in 2019 and says it "leveraged our expertise in running NVIDIA GPUs" to build a cloud; its FY2025 10-K dates to 2020. Ethereum was mined on general-purpose GPUs and a render farm runs on the same parts, so the reasonable reading is that the mining fleet became the first cloud; the 10-K says only that the "crypto mining offerings" were discontinued. None of it had anything to do with bitcoin.
Two other miners separated the businesses outright. Crusoe sold its bitcoin mining operation to NYDIG in March 2025; Northern Data sold its Peak Mining subsidiary in November 2025 before Rumble closed its acquisition of the remainder in June 2026. Those are corporate separations of two asset classes, and they say nothing about either's value.
Interconnection timelines have grown longer than AI training roadmaps, contracted megawatts have become the buildout's scarcest input, and accelerators ship faster than the grid can absorb them. ERCOT said on June 18, 2026, that it is tracking more than 438,000 MW of large-load requests, nearly 89 percent from data centers (ERCOT release). The same day, FERC sent show-cause orders to all six regional grid operators it regulates, a process this publication has covered.
There are several ways to compress time to power. Generation behind the meter is one, and the turbine order book runs years deep; in Texas, a co-located net-metering arrangement still requires an ERCOT study and commission approval, so it shortens the path without leaving the process (ERCOT). Splitting one training job across buildings that energize at different times is another. The most valuable is starting from an existing electrical footprint rather than virgin land and a fresh request.
In July 2025, CoreWeave agreed to acquire Core Scientific, its landlord, in an all-stock deal at 0.1235 CoreWeave shares per Core Scientific share. At the October 30 special meeting, 20,752,327 shares voted for and 203,451,498 against, and the agreement was terminated the same day. The filings record the rejection.
A 20-year lease signed in 2026 takes that interconnection away from any other claimant until the late 2040s, including scientific supercomputing, and the tenants are the same buyers already pre-purchasing capacity at every layer of the stack.
Count megawatts by legal and physical state, not by the noun in a press release. The dates on which the contracted column is scheduled to become the operating one are the numbers to track: Riot's first 96 MW to its frontier-lab tenant in December 2027, TeraWulf's Anthropic capacity from the second half of 2027, Hut 8's first River Bend hall in the second quarter of 2027, CleanSpark's first deliveries in the fourth quarter of 2027.